Plan-to-Implement process

Process documentation sample

Shows how I document the delivery lifecycle that business systems teams follow to plan, build and release changes to enterprise applications. It mirrors the structure of my real process documentation at Nutanix, with company-specific details made generic for confidentiality.

Item Details
Process owner Business Systems / IT PMO
Systems Jira, Confluence, application sandboxes (Salesforce, NetSuite, Workday and others), Integration platform (Boomi)
Audience Business analysts, developers, QA, product owners, business stakeholders
Version 2.1 · Published
Approvers Process owner, lead business analyst
Last reviewed Quarterly

Overview

Plan-to-Implement describes how a business request becomes a released change in an enterprise application. It covers intake and prioritisation, requirements, design, build, testing, user acceptance testing (UAT), deployment and hypercare, and the documentation produced at each step.

Scope

In scope: enhancement requests and projects for business applications and integrations, from intake to post-release support.

Out of scope: break-fix incidents (handled through the support queue) and infrastructure changes.

Process flow

flowchart TD
    A[Business request<br/>Jira intake] --> B[Triage and<br/>prioritisation]
    B --> C{Approved?}
    C -- No --> X[Closed / backlog]
    C -- Yes --> D[Requirements<br/>Confluence]
    D --> E[Solution design]
    E --> F[Build in sandbox]
    F --> G[QA testing]
    G --> H[UAT with<br/>business users]
    H --> I{Sign-off?}
    I -- No --> F
    I -- Yes --> J[Release and<br/>deployment]
    J --> K[Hypercare]
    K --> L[Documentation and<br/>training updated]

Roles and responsibilities

Role Responsibility
Business stakeholder Raises the request, joins UAT and signs off
Product owner / PMO Prioritises the backlog and plans releases
Business analyst Gathers requirements and writes user stories and acceptance criteria
Developer Designs and builds the change in a sandbox
QA Tests the change and logs defects
Technical writer Updates process docs, SOPs, release notes and training material

Process stages

1. Intake and prioritisation

  1. Requests are logged as Jira tickets with business justification, impacted applications and urgency.
  2. The PMO reviews requests weekly and scores them for value and effort.

2. Requirements and design

  1. The business analyst runs discovery sessions and documents requirements in Confluence, linked to the Jira epic.
  2. The solution design records impacted objects, integrations, data changes and security.

3. Build and test

  1. Developers build in a sandbox and link commits or change sets to the Jira story.
  2. QA runs functional and regression tests; defects are logged and fixed before UAT.

4. UAT and sign-off

  1. Business users test against UAT scripts in a full-copy sandbox.
  2. Sign-off is recorded on the Jira ticket before the change is scheduled for release.

Documentation checkpoint

UAT can't start until the updated process document and SOP are linked to the epic, so testers follow the same steps users will.

5. Release and hypercare

  1. Approved changes are deployed in the scheduled release window, following the deployment checklist.
  2. During hypercare (usually two weeks), the project team monitors issues and answers user questions.
  3. Release notes are published and the knowledge base is updated.

Documentation produced

Stage Artefacts
Requirements Business requirements, user stories, acceptance criteria
Design Solution design, integration specification, data mapping
Testing Test cases, UAT scripts, sign-off record
Release Release notes, deployment checklist, updated SOPs and process flows

Controls and KPIs

  • Lead time – from approved request to release
  • Defects found in UAT vs production
  • Release success rate – releases without rollback
  • Documentation completeness – epics with linked, up-to-date docs at release